Construction Of NDDRC Centre In Tiko : National Coordinator Evaluates Progress
- Par Kunyui NGONMENYUI
- 17 août 2021 16:43
- 0 Likes
Work is estimated at 65 per cent and the contractor said they will deliver on the deadline of October 30, 2021.
Ongoing works at the National Disarmament, Demobilization and Reintegration Committee (NDDRC) South West Centre in Tiko has been estimated at 65 per cent. This information was given to the National Coordinator, Fai Yengo Francis on Saturday August 14, 2021, in Tiko as he evaluated the level of progress in construction. The project being implementing by Enviro Construction Company, started in March 2021 and will last for nine months. Cedric Martin, the contractor, said they will respect the deadline and ensure the work is completed on October 30, 2021, the stipulated deadline.
In a guided tour in the premises, Cedric Martin explained at each stage what is has been done, what is being done and what is left to be done. He noted that they have observed a five per cent delay as a result of the heavy rains in Tiko. He however maintained that they will ensure the edifice is completed given the importance of the project to the State of Cameroon.
Fai Yengo Francis, National Coordinator of NDDRC, noted with satisfaction the progress of work. He appealed to those still in the bushes with arms to drop them and join the NDDRC South West Centre which is presently operational in Buea. He called on all Cameroonians to join him in championing for pea...
Cet article complet est réservé aux abonnés
Déjà abonné ? Identifiez-vous >
Accédez en illimité à Cameroon Tribune Digital à partir de 26250 FCFA
Je M'abonne1 minute suffit pour vous abonner à Cameroon Tribune Digital !
- Votre numéro spécial cameroon-tribune en version numérique
- Des encarts
- Des appels d'offres exclusives
- D'avant-première (accès 24h avant la publication)
- Des éditions consultables sur tous supports (smartphone, tablettes, PC)
Commentaires